Friday, January 16, 2009

Schedule of Building Progress

Monday, February 2
Concrete stain worship area (everybody out)
Tape and mud continues in BK area
CT cabinet arrives at Butler Supply

Tuesday, February 3
CT cabinet is set ready for wiring
Floors are finished
Govro finishes main bathrooms
Missouri Natural Gas sets meter

Wednesday, February 4
Ameren pulls wire, sets transformer, and hooks to CT cabinet
Govro sets toilets and dividers
Carpeting on risers, back hall, coffee shop

Thursday, February 5
Govro does bathroom sinks.
Crystal fires up our heating units.
Savage Electric fires up our lighting system
Trim goes on all walls
Small detail work and preparations on stage

Friday, February 6
Dozens of details like mounting paper towel dispensers, toilet paper racks, etc.

Saturday, February 7
Dozens more details. You can help.

Sunday, February 8
God is in business!!!
9:00 Rob Pierce preaching debut on John 10:10
10:45 Ricky Horton of the St. Louis Cardinals
12:00 MAC athletes eat at E-Hall.

Is this crazy? YES
Is it possible? Philippians 4:13

1 comments:

Tim Gray said...

Tough day for the floor stainers. Since there is no heat in the building, the stain is not drying as fast as usual. May be a late night for the Springfield boys. CT cabinet is sitting on a truck in St. Louis. It will be here first thing Tuesday morning and set and wired by noon. Come on, Ameren.